A representative sample of recent project types across commissioning, installation, design review, measurement, and reliability. Client names withheld; scope and systems are real.

Commissioning & Start-up

Multi-Unit Compressor Station

Permian Basin, TX

Full E&I commissioning on a 3-unit Cat 3616 compression facility — loop checks, ESD functional testing, DCS I/O verification, and completions package assembled in Hexagon Smart Completions. Zero punch items at client acceptance.

Cat 3616HexagonESD TestingLoop Checks
Measurement & Commissioning

Gas Custody Transfer Facility

Gulf Coast, TX

Flow computer configuration and meter factor verification for a 4-run fiscal measurement skid. Gas chromatograph commissioning, SCADA register map confirmation, and full custody transfer documentation delivered to client's document control system.

SCADAFlow ComputerGC Commissioning
Design Review

Gas Processing Plant P&ID Review

Delaware Basin, NM

Pre-construction P&ID and loop drawing audit on a 200 MMSCFD gas processing facility. Formal comment register with 47 engineering comments issued before first steel. All dispositions resolved before mobilization — zero field-found design errors at loop check.

P&ID ReviewLoop DrawingsInstrument Index
E&I Installation

Compressor Station E&I Build-out

Permian Basin, TX

Conduit, cable tray, instrument mounting, panel wiring and termination for a greenfield compression station. Work performed under licensed electrical supervision. Handed directly to commissioning crew — no punch items from contractor-to-comm handoff.

Conduit & TrayPanel WiringLicensed Supervision
Reliability & Maintenance

4-Station Annual PM Program

Gulf Coast, TX

Annual instrument calibration program across four compressor stations under a standing MSA. Transmitter as-found/as-left documentation, ESD annual functional testing, gas detector bump and calibration. All records logged directly into client's CMMS — SAP PM work orders closed within 48 hours of field completion.

SAP CMMSAnnual PMESD TestingMSA
Bluebeam & Field Engineering

Midstream Facility Completions Package

Eagle Ford, TX

Bluebeam Studio Session setup and redline management for a 150-loop midstream gas facility. Loop card buildout in Revu, digital punchlist, and completions package formatted to client's Aconex document control submission requirements. First-pass acceptance on all 11 document packages.

Bluebeam RevuAconex150 Loops

Have a Project Like This?

Tell us your scope. We'll respond within one business day. MSA available on request.